Peachtree Creek Capacity Relief Project – Liddell Drive Equalization Facility

NPU: F                                      Council District: 6

The project will address overflows in the Peachtree Creek Sewers. A 10-million-gallon sewer storage tank will be constructed near Liddell Drive to capture sewer overflow. Once flow decreases in the sewers, water stored in the tank will be discharged back to the sewage collection system at a controlled rate. Work began in March 2013.