Tanyard Creek CSO
The Tanyard Creek CSO Facility
is located at 155 Loring Drive on a small site at the boundary of
the Loring Heights residential area, and is bounded by I-75 to the
east and Deering Road to the south. Constructed in 1994, the Tanyard
Creek CSO Facility serves a west area combined sewershed of approximately
1,955 acres and has a maximum overflow capacity of 3,600 mgd. Incoming
flow is brought to the facility and dry weather flow is routed to
the 48-inch Orme Street interceptor that leads to the RM Clayton
WRC. Wet weather flow is routed through the CSO facility for treatment
and then released to a concrete discharge channel that is approximately
0.8 mile long, extends under I-75, and ultimately leads to Tanyard
Creek. Existing treatment at the Tanyard Creek CSO Facility consists
of coarse screening, fine screening, and disinfection by sodium hypochlorite
to kill bacteria and other pathogens. As part of the short-term remedial
measures initiatives, the location of hypochlorite dosing will be
moved upstream of the facility to allow for more contact time between
the hypochlorite and CSO.